Project Overview
Proposed Improvements
The proposed improvements involve replacing the existing FM 1560 solid concrete rail with an open rail from Riggs Road to SH-16.
Project Schedule
Work is scheduled to commence on July 13, 2020 and be completed by the end of August 2020. Timeline is subject to change due to weather conditions and unforeseen circumstances.
Traffic Closures
Currently, this project has one scheduled traffic closure on July 13, 2020 from 9 p.m. to 5 a.m. , which affects the following lanes:
- SH-16 southbound designated right turn lane; and,
- FM 1560 right lane, in both eastbound and westbound directions.
This closure is weather permitting and subject to change.
Construction Zone
During project construction, motorists will continue to be able to travel through FM 1560 with minor changes. All lanes on FM 1560 will be open but will be narrowed slightly to adjust for construction work zones.
Stay Connected!
Stay connected on TxDOT San Antonio’s Twitter feed or the GoAhead! Blog for ongoing construction and traffic updates.
CONTACT INFORMATION
Jennifer Serold
Public Information Officer
(210) 262-9348
jennifer.serold@txdot.gov
SAN ANTONIO DISTRICT
4615 N.W. Loop 410
San Antonio, TX 78229